A carport installer should accept a site handover once the current installation drawings, measured post positions and base levels, access arrangements and open changes have been checked and recorded. Confirm who can release the work and which activities the release covers. A general contractor may have finished the driveway while verification of the supporting base is still pending, and the installer and carrier may be booked for different times.
Carport Prestige with covered parking and an enclosed storage section.Start With the Issued Installation Drawings
Identify the Drawing Revision for This Site
Put the order reference, model, configuration and work area on the carport site handover checklist. Attach the current drawing issued for installation and the applicable installation instructions. Check the drawing number and revision against the copy held by the site team. On a development with similar driveways, confirm the plot as well as the model. Include the drawing pages for the post layout, connection details and any selected options that affect the workface, the area being handed over for work.
The UFGS quality control specification’s preparatory phase gives an example of checking approved submittals, earlier work and delivery arrangements together. For your carport, carry forward the agreed supply and site-work responsibilities and give each one a record to check. If your team needs the original scope decision, return to the metal carport quote comparison and confirm what made it into the order.
Name the People Who Can Release the Work
Identify who hands over the area, who verifies the site work and who authorizes each next activity. A general contractor may coordinate the handover while a civil contractor or surveyor provides the measurements and base records. The installer checks the received information against the planned work and raises discrepancies. Name the person authorized to resolve each issue under the project agreement and the person who tells the carrier whether it can arrive. Give the installer and receiving team access to the same current record.
Check access, receiving time, unloading and storage.
Record the delivery release
List the approved activities and receiving contact.
Check the workface, base evidence and open changes.
Record the installation release
Identify the released area and any remaining holds.
If a check is open Keep the affected activity on hold and record who will clear it.
Verify the Workface Against the Drawings
Check Post Positions and Bearing Levels
Carport site preparation should leave the installer with a way to find each post, identify the supporting surface and verify what was built. Start with the drawing’s grid and level reference, or datum. Record the measured post or anchor position against the corresponding drawing point. For each relevant base, distinguish the finished paving level from the bearing level, the surface designated to support the post. The AISC Code of Standard Practice for steelwork gives an example of using established lines and benchmarks and surveying as-built anchor locations.
-
Grid reference. Use the same axes on the drawing and survey.
-
Drawing position. Find the approved location for the affected post.
-
Measured position. Identify the discrepancy and reference it to the grid.
-
Finished paving. Record the surrounding surface level.
-
Bearing surface. Record the specified support level at the post.
-
Common datum. Reference both readings to the same project mark.
Conceptual plan and section. The offset is exaggerated for clarity. Use the project drawing for dimensions and fixing details.
Check the project’s carport foundation requirements against the available site inspection or construction records. Where finished paving conceals the support, ask the responsible site team for evidence of the base and fixing conditions before releasing installation. Match the drawing reference and post or bay to each record. Include actual obstructions at the workface, such as a drain inlet or buried service identified by the site team, where they affect the agreed installation area.
Match the Approved Carport Configuration
Carport Metta, our freestanding steel carport for one vehicle, has four posts and a fixed steel roof. Its published 5.3 × 3.2 m size identifies the standard configuration. Use the issued plan for the positions of the four supports and compare each with the site record. On a driveway where the paving slopes, carry both elevations into the handover so the installer can identify the working surface and the specified base.
Carport Metta at a driveway, with the front posts and fixed roof in view.
Carport Metta from the side, showing the post line beside the parking bay.Carport Prestige, our aluminum carport with storage options, uses a freestanding aluminum frame and a fixed roof. When the order includes a storage enclosure, check the storage side, door position and planned receiving point for roof drainage against the approved layout. Show an outlet discrepancy on the drawing and ask the responsible party to confirm its effect on the project. Our carport collection lets you compare steel and aluminum carport configurations when confirming the model on the handover record.
If the order came through a metal carport manufacturer supporting distributors and local installers, ask the distributor or wholesaler to pass the current order drawings and option list to the installer. Give the receiving team the matching delivery references.
Agree Delivery and Unloading Before Mobilization
Confirm Access and the Unloading Window
Confirm the carport delivery date and agreed unloading window with the carrier and site receiver. Check the route to the unloading point, gate restrictions, people using the site and the location reserved for temporary storage. Assign a site contact for the driver and share the agreed route before arrival. The UK HSE guidance on loading and unloading gives practical checks for keeping people outside the operation and providing a suitable unloading area.
-
Vehicle entrance. Confirm the route to the gate and the agreed arrival window.
-
Unloading area. Confirm the location and the person receiving the load.
-
Temporary storage. Agree where packs will be placed and how they will be identified.
-
Pedestrian path. Keep it separate from the unloading activity.
Illustrative site plan. The receiving team and carrier confirm the actual routes, storage area and activity window.
For an international order, the importer can pass the exporter’s packing references and handling information to the local carrier and receiver. Ask the carrier and site team to confirm the agreed unloading arrangements, including who provides any equipment required by their plan. For temporary storage, check which packs can go where and how the agreed protection and identification will be kept until installation.
On a B2B order delivered to several plots, number the intended storage areas on the receiving plan. Give the receiver the pack references to check against the delivery note for each plot. The crew can then locate the correct packs as each plot is released, even when another plot is still on hold.
Separate Delivery From Installation Release
Record arrival, unloading and temporary storage against the activity and area the site team authorizes. If only that scope is ready, the receiver can arrange it once the conditions and written approval are in place. Carport installation can be released after the current drawings, inspected workface and relevant open changes have been checked and the authorized person has recorded the decision. For example, a confirmed unloading bay and receiving contact may let the truck arrive while a revised outlet location still needs review. List the affected installation area as a hold and give the installer the current status before mobilization.
Record Site Changes and Release the Work
Refer the Discrepancy to the Named Approver
Use a dated photo, drawing number and revision, and the exact location to raise a discrepancy. Put the specified position and the field measurement side by side, using the same reference. State which work is affected and the response needed. A marked-up drawing can accompany a written request for information, or RFI. The Caltrans control-of-work manual illustrates a written route for reporting a changed condition and getting a recorded response. Use your own project’s required process and named approver.
For example, if the surveyed drainage inlet now falls within the area reserved for access to the storage doors, mark both on the same plan. Ask the project’s designated reviewer to confirm where the outlet is to discharge and which activities can proceed while that point is being resolved.
If a local fabricator needs to review a changed connection, share the measured condition with the drawing issuer and route any proposal to the designated design authority. For a custom carport supplied through an OEM or ODM order, include the approved option and part references. When you work with a Chinese carport factory supporting custom project configuration reviews, that information helps the factory check which supplied parts or interfaces the change could affect.
Record the Release Scope and Remaining Holds
| Issue and location | Site evidence | Reviewer | Work permitted | Close with |
|---|---|---|---|---|
| Post position differs | Marked plan, revision and field reading on the same grid. | Project design authority for the affected connection. | Pause work at the affected post. Other activities follow their written release. | Written disposition and a check at the post. |
| Base record missing | For the affected bay, list the inspection or construction record needed. | Site lead responsible for base verification. | Hold installation in the bay. Receive goods if separately authorized. | Matching base record and documented release. |
| Unloading window unconfirmed | Log the requested time, route and receiving contact. | Carrier and authorized site receiver. | Keep the delivery off that schedule until the arrangements are confirmed. | Written window and confirmation to the driver. |
Use the drawing revision and work area on each entry. Keep the written decision with the release record.
Close a hold by recording the approved disposition, the revised drawing if applicable, and the result of rechecking the affected condition. Give the installer a dated release that names the work area, authorized activities and any remaining holds. Send the update to everyone using the earlier record. If the installation date changes, tell the installer and reconfirm any receiving or storage arrangement affected by the new sequence.
We coordinate order-specific product information with our international partners from our own factory in China. For the product scope, explore our outdoor structure and product systems. For component matching and packing, see our carport and outdoor structure manufacturing facility. The project team uses its local measurements and approval process to document the site release.
Frequently Asked Questions
What should a carport site handover include?
Include the issued drawing, measured workface, foundation records, delivery arrangements, responsible contacts and the written scope of release.
Is finished paving enough to release installation?
Verify the supporting base, post positions, levels and specified fixing conditions. Include the relevant approval or inspection records with the handover.
Can we unload before the installation area is ready?
Confirm access, an unloading area, suitable temporary storage and permission for those activities. Keep delivery and installation releases as separate entries.
What if an anchor position differs from the drawing?
Record the measured position and drawing revision and hold the affected work. Ask the designated approver for a written disposition before proceeding.
Who should confirm the carport foundation requirements?
The project’s designated designer or engineer confirms the requirements. Obtain the corresponding site verification record for the supporting base.
Which levels should the installer record?
Record finished paving and the actual bearing surface at the relevant posts. Reference the same site datum as the issued drawing.
Can our customer keep the existing driveway paving?
The customer may be able to keep it. Have the project team verify the supporting structure, approved fixing detail, levels and drainage at the proposed positions.
What if the delivery window moves?
Reconfirm the receiving contact, access, unloading area and temporary storage with the carrier and site team. Update the handover record before the vehicle arrives.
Materials, hardware, installation conditions, order details and final customization are confirmed for each project.